What's Built at June Lake in Spring Hill, and What a Buyer Is Waiting On

June Lake is often described as a town center with homes around it. Five years after groundbreaking, the homes are well ahead of the town center. Saddlewalk is closing houses and framing townhomes, while the first stores, offices and the lake loop are scheduled for 2027 or later. For a buyer comparing June Lake with established parts of Spring Hill, that order is the deal. You can buy a new Williamson County home for much less than the county median, and in exchange you live through the years when the rest of the plan gets built. Which pod and lot you choose decides how long that stretch lasts for you.

Five years into a twenty-year plan

Southeast Venture manages June Lake, a 775-acre master plan on Spring Hill's northeast corner in Williamson County, built around the I-65 Exit 55 interchange. The full entitlements allow more than 2,900 residential units, 3.9 million square feet of Class A office space, nearly 1.3 million square feet of retail and restaurant space, and 400 hotel rooms. Ground broke in June 2021. When the first phase was rezoned in August 2020, Southeast Venture called it a 20-year project.

The road arrived before most of the buildings. The diverging-diamond interchange at Buckner Road had its ribbon-cutting on May 29, 2024. The Williamson Herald reported a total cost of $56.8 million, shared by the City of Spring Hill and TDOT, with officials saying it would serve the June Lake development. June Lake Boulevard is the 2.25-mile connection from Buckner Lane to Lewisburg Pike. It already carries about 17,000 cars a day, a traffic count the developer cited at a city meeting this spring.

The city's own records show how far the buildings have caught up. A September 2025 list of vested sewer commitments, which Spring Hill compiled for state regulators, showed 2,579 of June Lake's 2,926 committed homes still to be built. That means roughly 350 homes were connected at the time. The same list counted the entire commercial program as unbuilt. Springhillian's June Lake development tracker works that out to about 12% of the homes and essentially none of the commercial space as of that list. Most of what follows has happened since then.

Saddlewalk is where the building is happening

Signature Homes is building Saddlewalk, its first June Lake neighborhood, with roughly 400 single-family homes and townhomes plus an amenity center. As of the developer's August update, Pod B was sold out, move-ins in Pod A had started in July, and the first townhome buildings in Pod E were framing. Three model homes were scheduled to open in October. The city's August 2026 building report lists about two dozen new residential permits labeled Saddlewalk or June Lake, on Marston Avenue, Saint Clair Avenue, Sage Street, Lotus Lane and Buckner Lane. Construction valuations on those permits ran from the high $380,000s on smaller townhome lots to the $900,000s on larger single-family homes.

On its website, Signature Homes prices its main Saddlewalk series from $690,000 to $1,380,000, and its cottage plans start lower. Lot premiums and options move those numbers, so read them as a range and not a quote. Tudor Homes is building The Preserve, a smaller pocket of 28 custom single-family homes of about 3,000 to 3,500 square feet near Buckner and Twin Lakes.

Compare those prices with the county. Greater Nashville Realtors' quarterly county data for the third quarter of 2026, July through September, puts Williamson County's residential median at $1,075,000. Maury County's median for the same quarter was $440,000. Most of Saddlewalk's advertised range is inside Williamson County and below that county median. Part of that discount is location, and part is the timeline. Buyers of these homes are moving in before the restaurants, offices and lake loop that the long-term plan is built around.

The wider market has also given buyers more room. In its October 2026 report, released November 9, Greater Nashville Realtors put the October single-family median for its nine-county region at $499,990, down 3% from October 2025. Active listings rose 8% year over year to 15,379, which equals 6.83 months of inventory, and single-family homes averaged 61 days on market. A buyer who can choose among established resale homes has a real alternative to waiting on a new build, and builders know it.

The phase you pick sets your timeline

Saddlewalk's sections are at different stages this fall. Pod A has residents and Pod B has finished selling. The Pod E townhomes have walls going up and model homes to tour. The next pieces are still at the roads-and-pipes stage. On November 2, the Board of Mayor and Aldermen voted to let Signature move ahead with infrastructure for Pod E Section 3, a 75-lot townhome phase, and for Windfall. The staff memo and the Tennessee Record's meeting recap are the public record of that vote.

Windfall is Signature's next neighborhood, with about 400 homes planned on roughly 120 acres south of June Lake Boulevard. Its first phase was approved in mid-2025, and its houses have not yet shown up in the permit surge that Saddlewalk is seeing. Lifestyle Communities announced a 509-unit rental phase in January 2025. That phase is still committed, and the developer says its first phase will start once sewer capacity is available.

This leaves a buyer with a choice. A home in a section that is already building comes with a closing date the builder can put on paper now. A homesite in a later section gives you a wider choice of lots, but your date depends on how fast that section moves. Before you compare floor plans, ask Signature for the projected completion date on the specific lot you are looking at, and compare that date with the time a resale would take to close.

Windfall will also change the map next door. Its new collector road runs south from June Lake Boulevard and connects where Spring Station Drive now dead-ends at the top of Wades Grove. The mayor confirmed that connection at an April board meeting. If you are looking at a resale on that end of Wades Grove, a quiet dead-end street is set to become a through connection.

The commercial corner is on a 2027 calendar

The first commercial district is Pod K, on June Lake Boulevard east of Buckner Lane. Its streets, water and sewer are complete, and as of early November vertical construction had started. These are the dates that have been made public for that corner and for the amenities around it:

  1. Buckner Lane's final widening segment, which completes the five-lane road with trails and sidewalks from Thompson Station Road down to Duplex Road, was expected to finish in December 2026 according to the city's October capital-projects report.
  2. The June Lake Trail, a paved one-mile loop around the lake with a scenic overlook, is expected to open in spring 2027.
  3. Liberty Federal Credit Union is building a branch at 2600 Buckner Lane under a permit issued August 27, 2026, and its builder is aiming for summer 2027.
  4. The June Lake Collective, two buildings of about 15,823 square feet at 3060 June Lake Boulevard, is pre-leasing retail and restaurant space for a summer 2027 completion.
  5. Quarterly public tours of the historic Pointer Cemetery are expected to start in 2027 under an agreement between the Alexander family and the Battle of Franklin Trust, the group that operates Carnton and the Carter House.

Two more buildings are on that corner. Heartland Dental is building a 5,000-square-foot office at 3030 June Lake Boulevard under a permit issued August 12, 2026, and it will be the development's first healthcare provider. Image Studios is a salon-suite building of about 7,700 square feet at 3070 June Lake Boulevard. The Goddard School has been approved and announced for the Buckner and June Lake corner. It was first pitched for a summer 2025 groundbreaking, and no new construction date has been set. Across the boulevard is the planned Hy-Vee site. The project has not moved through City Hall since 2023.

Solstice at June Lake, 227 apartments at 2400 Buckner Lane, is open, and June Lake is now on the Street Food Finder food-truck rotation. Some infrastructure was also built early. When TDOT built the boulevard, the city approved a change order to bury a 12-foot-wide pedestrian culvert just west of I-65 so the Aenon Creek greenway could pass under the road. It cost $502,228.54, and June Lake's development entity agreed to repay the city. About 3,000 feet of that greenway has been built so far, and the underpass is waiting for the trail to reach it.

Questions buyers ask about June Lake

Is June Lake in Williamson County or Maury County? June Lake is on Spring Hill's northeast corner in Williamson County, west of I-65 around Exit 55. Spring Hill crosses the county line, and our post on what the county line costs in Spring Hill covers why that matters when you compare listings.

Which builders are building homes at June Lake now? Signature Homes is the production builder in Saddlewalk and Windfall. Tudor Homes is building the 28-home Preserve.

When will June Lake have restaurants? The June Lake Collective is pre-leasing for a summer 2027 completion, and its tenant names will tell you which restaurants are coming. Food trucks come to Solstice in the meantime.

What should I compare a Saddlewalk home against? Compare it with resale homes on the Williamson County side of Spring Hill at the same price, where the amenities are already built. Then weigh what the price difference buys against the 2027 calendar above.

Choosing a new home in a master plan this early depends on the builder's schedule as much as the floor plan, and that is where Susan's builder-side experience and relationships do their work. If you are weighing a Saddlewalk lot, a Preserve homesite or an established Spring Hill resale, Susan Gregory Group can help you find out which lots have a real move-in date and how the price compares with what is already built nearby. Request a consultation, and we will look at June Lake with you.